1. Adjustment of Waste Water Olefins Plant
This project includes engineering and construction of a system to remove hydrocarbons, solids and sulfides of residual waters.
Also it includes the starting of the plant and the training of the personnel who will operate the Olefins Plants.
2. EPC for the Main Station and clusters
This project includes the development of the detail engineering and construction of the Main Station for crude reception, with a production capacity of 200.000 b/d; and 32 clusters, of 6 to 24 horizontal wells each one, located in the production block in San Diego de Cabrutica.
This was the individual contract of greatest spread of Sincor upstream, with an amount of 320 MM$, executed by the Joint Venture CPO- Yanes & Asociados, the Canadian company SNC Lavalin and a local contractor.
3. Residual Water Treatment Plant
This project includes the engineering and construction of The Waste Water Treatment Plant in Ameriven Upgrader Complex in Jose, Anzoategui state.
The treatment plant that will gather the rainwater and waste waters of heavy crude refinement for process more than 1200 gal/min in three main process system: the Accidentally Oily Sewer System (AOS), the Oily Water Sewer system and the High Biochemical Oxygen Demand System (High BOD),
The plant has also a system of mud harvesting and systems for the addition of chemistries and polymers to facilitate the treatment of served waters. This project, for Alvica Group, is developed in a Joint Venture with Eimco Process.
4. Sincor Administration Complex
This project includes the execution of the Administrator Complex, present seat of Sincor in the Jose Upgrader, designed on approval of explosions.
The Complex is made up of nine buildings that occupy an approximated area of 16,000 m2 of construction:
- Administrative building (approximated area of 3.900 m2)
- Maintenance and Deposit building (approximated area of 1.300 m2)
- Laboratory building (approximated area of 1.300 m2)
- First aid building (approximated area of 340 m2)
- Deposit chemistry building (approximated area of 1.800 m2)
- Coffee bar building (approximated area of 930 m2)
- Clothes building (approximated area of 780 m2)
- Main house building (approximated area of 280 m2)
- Access constructions
This project was executed in Partnership with Preacero Pellizari company.
5. Radio stations
Engineering and Construction of radio station for cellular telephony in all over the country, contributing with the national cover extension plan developed by our client. We also offered them permissions, execution logistic for each ERB and revision or structural reinforcement and/or design of construction in site for the adjustment of the ERB.
|