PROJECTS / Infraestructure Sectors

1. SINCOR Administration Complex

This project includes the execution of the Administrator Complex, present seat of SINCOR in the Jose Upgrader, designed on approval of explosions. The Complex is made up of nine buildings that occupy an approximated area of 16,000 m2 of construction:

Administrative building (approximated area of 3.900 m2)

Maintenance and Deposit building (approximated area of 1.300 m2)

Laboratory building (approximated area of 1.300 m2)

First aid building (approximated area of 340 m2)

Deposit chemistry building (approximated area of 1.800 m2)

Coffee bar building (approximated area of 930 m2)

Clothes building (approximated area of 780 m2)

Main house building (approximated area of 280 m2)

Access constructions

This project was executed in Partnership with Preacero Pellizari company.


2. Radio stations

Engineering and Construction of radio station for cellular telephony in all over the country, contributing with the national cover extension plan developed by our client. We also offered them permissions, execution logistic for each ERB and revision or structural reinforcement and/or design of construction in site for the adjustment of the ERB.

Year: 1.997
Total: Seventeen (17) Radio Constructed Bases
Amount of contract: BS. 1.721.887.795, 49 - U$. 3,514,343.61
Man Hours: 91.800,00

Year: 1.998
Total: Thirteen (13) Radio Bases Constructed
Amount of contract: BS. 1.583.316.300,94 - U$. 2,879,175.70
Man Hours: 70.200,00

Year: 1.999
Total: Nine (9) Radio Bases Constructed
Amount of contract: BS. 1.118.996.822,50 - U$1,838,006.64
Man Hours: 70.600,00

Year: 2000
Total: Five (5) Radio bases Constructed
Amount of contract: BS. 939.238.754,50 - U$ 1,377,142.54
Man Hours: 27.000,00


3. The Snack Plant

In Santa Cruz de Aragua was constructed the snack plant. This projects includes the construction of the main shed of processes and the services building, in an approximated area of 6.000 m2.

4. El Tiempo News Paper, new seat

We constructed the new seat of this important newspaper on the east of the country. The first stage was concluded in the year 2000 and the second phase of the project in the middle of the year 2002. The construction included: The rotating building factory, the warehouse building, the administrative building and outer works.

5. Pepsi-Sopresa Bottling plant

The modern Pepsi bottling plant in Zulia state was designed and constructed to a cost of 16 MM $, with an approximated area of three hectares of construction. This project was executed in partnership with Guinand y Brillembourg company.

6. EPC Infrastructure of Radio stations Base, for cellular telephony in Movilnet

Location

Caracas, central states, Andean states and Zulia state constituted the more important centers of location of this one development. Total Radio Constructed Bases: 52 Units.

Amount of contract
Investment: Bs. 6.265,94 MM - U$10.571.047,73
Man Hour/Direct: 280.800,00
Man Hour/Indirect: 84.240,00
Modality of the Contract: Unitary Price

Performance
Date of beginning the project: March, 1997
Date of Culmination: March, 2003

Management
Movilnet Management: Eng. Zaida Rivas Representing
Client: Eng. Sergio Sequeda.
Project Manager of the Partnership: Eng. Angel Bueno
Summary: The Project included Details Engineering, attendance in the transaction of permissions, construction of the infrastructure for the radio bases for cellular telephony by the Development of Movilnet network.


7. Adjustment, Optimization of Spaces and other services associated to the Radio bases installations of cellular telephony Movilnet



Location: Capital region, Andean states, Zulia State, Eastern Zone of the country.
Amount of contract:
Total Investment: Bs. 2,372.02 MM - $ 3.164.367,62
Man Hours: 100.800,00 Direct
Modality of contract: Unitary Price
Performance:
Date of Beginning the Project: March, 1998
Date of Culmination: March, 2003

Management:
Movilnet Management: Ing. Zaida Rivas Representing
Client: Eng. Sergio Sequeda
Manager Project: Eng. Angel Bueno
Summary: The project included details engineering, construction of civil works and electrical works relative to the extension and/or adaptation of the radio bases; electrical attacks including measurement modules.


8. EPC-buildings of Control - Project Development Dación de Lasmo Field

Location: Dación field El Tigre, Anzoátegui state

Amount of contract:
Total Investment: BS. 2,156.02 MM
Man Hours: 69.200,00 Direct

Management:
Lasmo Management: Eng. Juan Carlos Coral
Representing Client: Eng. Juan Carlos Coral
Project Manager: Eng. Benjamin Isamit
Summary: EPC Constructions of Control and Systems of Data voice-CTV Access Control and Control for all the facilities in the project.

Performance
Date of Beginning: November 1998
Date of Culmination: September 2000